Konsolidat — Roadmap

Last updated: 2026-06-19

See ../prd/README.md for the per-feature PRD index.

Status Summary

AreaStatus
Data pipeline (Bronze → Silver → Gold)Done — 85 dbt models, 150+ tests
Consolidation (FX, IC elimination, CTA, NCI)Done — IFRS/GAAP compliant
Hierarchy, equity method, acquisition/disposalDone
Allocations (multi-step cascade, reciprocal, tiered)Done — dynamic N-step engine
Budget write-back (Excel → CH)Done — EPMSAVE() from Excel + Frappe API
Budget write-back (CH → ERP)Not started — push approved budget to D365 BudgetRegisterEntries
Scenario managementDone — budget/forecast/whatif via API
Variance analysisDone — actual vs budget with favorable logic
Excel VBA integrationDone — =EPM() + 5 functions, ODBC + REST
Frappe app (konsol)Done — DocTypes, ClickHouse sync, background jobs
Docs site (MkDocs Material)Done — konsolid.at, 40+ pages
Custom domainDone — konsolid.at on GitHub Pages
One-click deployDonegit clone && ./deploy.sh, 9 Docker services
Multi-ERP canonical staging + D365 F&O adapterDone — 7 canonical models, 16 D365 F&O adapter models (PR #10)
Multi-ERP connectors (SAP, D365 BC, ERPNext)In progress — ERPNext connector done (source-erpnext/ + 7 staging models); SAP / D365 BC remaining
FastAPI / Streamlit / DagsterRetired — replaced by Frappe konsol app
Dynamic schema (dimensions, measures, facts)In progress — Dimension + Measure + Fact registries done, API generalisation done; ClickHouse auto-DDL on dimension/measure save remaining
Security / Entra ID SSONot started
Excel Online Add-in (Office.js)Done — Task pane add-in, pipeline orchestration, Frappe session auth
Cash flow statementNot started
Multi-GAAPNot started
Rolling forecastsNot started
Consolidation enhancements (goodwill CTA, NCI in combos, disposal recycling)Not started
Allocation enhancements (circular, reciprocal)Not started
Planning enhancements (driver-based, recurring journals)Not started
Reporting enhancements (waterfall, trend, commentary)Not started

Phase 1: One-Click Deploy (~3 days) DONE

Full docker-compose stack + single deploy script. Completed in PRs #7 and #9.

  • 9 Docker services: Frappe backend/worker/scheduler, MariaDB, Redis (cache + queue), ClickHouse, Cube.js, Caddy
  • 2 one-shot init containers: configurator (site setup), dbt_init (seed + build)
  • deploy.sh — generates secrets, clones konsol, runs compose up, health checks
  • Caddy reverse proxy with auto-SSL
  • Static assets via gunicorn SharedDataMiddleware (PR #9)
  • Initial Setup Guide documentation
  • Subcommands: ./deploy.sh backup, restore, status, logs, down

Phase 2: Dynamic Schema — Dimensions, Measures & Facts (~5 days) IN PROGRESS

Make the data model fully registry-driven from Frappe. Adding a dimension, measure, or fact table should be a UI operation in Frappe Desk, not a code change across 6 files.

What's done

The dbt layer is fully dynamic — Dimension and Measure registries in Frappe drive dbt_project.yml vars, and macros (dim_select(), dim_group_by(), measure_select()) generate SQL from those vars. Gold models like gold_trial_balance already use them. Source-layer abstraction is complete (dim_select_from_source() maps ERP source columns to canonical dimension names).

What remains

The Frappe API is now registry-driven (epm_value takes a generic fact + dimensions dict, validated against the Fact/Dimension/Measure registries), and the Fact Registry applies ClickHouse DDL + dbt sources on publish. What remains is auto-applying ALTER TABLE ADD COLUMN on individual Dimension/Measure save (today a new dimension/measure still relies on a fact publish or dbt rebuild) and dynamic Budget Input form field generation.

2.1 Dimension Registry (1 day) DONE

  • Frappe Dimension doctype — on save, auto-generates dbt_project.yml vars.dimensions via dbt_config.py
  • Fields: dimension_name, source_column, label, cube_type, in_budget, allocation_role
  • Allocation engine uses allocation_role from dimension config
  • ClickHouse ALTER TABLE ADD COLUMN on dimension save (currently requires dbt rebuild)
  • Budget Input doctype field generation (dynamic via Frappe custom fields API)

2.2 Measure Registry (1 day) DONE

  • Frappe Measure doctype — on save, auto-generates dbt_project.yml vars.base_measures via dbt_config.py
  • Fields: measure_name, expression, label, cube_type
  • Default measures pre-seeded: period_debit, period_credit, period_net_amount, transaction_count
  • dbt macros (measure_select(), measure_passthrough()) consume measures dynamically
  • API response validates measure param against active Measure registry (currently hardcoded ALLOWED_MEASURES dict)
  • ClickHouse gold table columns auto-generated on measure save

2.3 Fact Registry (1.5 days) DONE

PRD: Fact Registry

  • Frappe Fact Table doctype: fact_name, source_type (ERP GL / Budget / Statistical / Sub-ledger), grain description, refresh_frequency
  • Core facts (pre-seeded, always present):
    • GL Journal Entries — debits/credits by account/period/entity (the universal financial fact)
    • Budget Input — budget submissions per cell
    • Variance Analysis — derived actual-vs-budget output
  • Statistical facts (customer-configurable):
    • Headcount — employees per cost center per period (for allocation drivers)
    • Area (sqm) — square metres per cost center (for facilities allocation)
    • Revenue by Product — for revenue-based allocation
  • Sub-ledger facts (for detailed reporting):
    • Accounts Payable — invoice-level detail for cash flow
    • Fixed Assets — asset register for depreciation / investing cash flow
    • Accounts Receivable — aging for working capital analysis
  • Each Fact Table defines: required dimensions, required measures, ClickHouse table name, dbt model name
  • On publish: generates ClickHouse staging table DDL + dbt source definition

2.4 API Generalisation (1 day) DONE

PRD: API Generalisation

  • Replace hardcoded cost_center, department params with generic dimensions dict
  • =EPM("USMF", 2024, "Q1", "401100", dimensions={"dim_cost_center": "CC001", "dim_project": "P01"})
  • measure parameter validates against active (Published) Measure registry
  • New fact parameter: resolves the source fact (wins over scenario); can query GL, budget, or statistical facts
  • ClickHouse query builder reads active dimensions/measures/facts from registry

Legacy named params (cost_center, department, dim_* kwargs) were removed, not mapped — callers must use the dimensions dict (see test_api_generalisation). The earlier "backward-compatible old named params" goal was dropped.

2.5 Source Layer Abstraction (0.5 days) DONE

  • dbt macro {{ dim_select_from_source() }} reads dimension list and generates extraction SQL per ERP
  • D365: auto-extract from LedgerDimensionValuesJson by source_column name
  • dim_select(), dim_group_by(), dim_partition_by() — generate SQL from dimension vars
  • SAP/ERPNext: each connector provides its own dimension mapping (see Phase 3)
  • Fact-specific source macros: GL extraction vs. budget extraction vs. statistical extraction

Phase 3: Multi-ERP Support (~8 weeks) IN PROGRESS

Konsolidat's silver/gold layers are already ERP-agnostic. The canonical staging interface, D365 F&O adapter, and ERPNext connector are complete, as are dimension harmonization and the Frappe Connector Registry. Remaining work is adding connectors for SAP (S/4HANA, ECC, B1) and D365 Business Central, plus budget write-back and scale (incremental extraction / clustering).

Note: D365 F&O and D365 Business Central are completely different products (different APIs, entity models, dimension systems). BC needs its own connector.

Work Breakdown

TaskEffortStatus
Canonical Staging Schema & Adapter Interface2 daysDone (PR #10) — 7 canonical models, UNION ALL from adapters
D365 F&O Adapter Refactor1 dayDone (PR #10) — 16 models renamed stg_d365_fo__*, canonical output
D365 F&O Budget Write-Back2 daysNot started — OData POST on budget approval
D365 Business Central Connector3 daysNot started — PRD: D365 BC
SAP S/4HANA Connector3 daysNot started — PRD: SAP S/4HANA
SAP ECC 6.0 Connector3 daysNot started — PRD: SAP ECC 6.0
SAP Business One Connector2 daysNot started — PRD: SAP B1
ERPNext Connector2 daysDonesource-erpnext/ Airbyte source + 7 stg_erpnext__* canonical-adapter models — PRD: ERPNext
Dimension Harmonization3 daysDonedim_harmonize_select() / dim_harmonize_joins() macros wired into canonical stg_gl_entries / stg_budget_entries, Connector Dimension Map doctype, gold_unmapped_dimension_values — PRD: Dimension Harmonization
Scale Architecture (50–500 LEs)5 daysPartial — bronze partitioning done, incremental extraction not started — PRD: Scale Architecture
Connector Registry (Frappe)2 daysDoneConnector doctype drives vars.erp_sources, records LEs (Connector Legal Entity) + dimension maps + Connector Health — PRD: Connector Registry

Dependency Graph

graph TD
A[Canonical Schema] --> B[D365 F&O Adapter]
A --> C[D365 Business Central]
A --> D[SAP S/4HANA]
A --> E[SAP ECC 6.0]
A --> F[SAP Business One]
A --> G[ERPNext]
B --> H[Dimension Harmonization]
C --> H
D --> H
H --> I[Scale 50-500 LEs]
I --> J[Connector Registry]

Connector Details

PRDConnectorAPIGL Source EntityBudget Write-Back TargetAirbyte Source
31D365 F&O (refactor)OData v2GeneralJournalAccountEntryBiEntitiesBudgetRegisterEntries (OData POST)Existing
32D365 Business CentralREST v2.0 / OData v4generalLedgerEntriesbudgets (REST API)Airbyte BC connector
33SAP S/4HANAOData v4 (CDS views)I_JournalEntry, I_GLAccountLineItemA_BudgetPeriodBalance (CDS)Airbyte SAP OData
34SAP ECC 6.0RFC/BAPI or IDocBSEG + BKPF tablesBAPI_BUDGET_POST (RFC)Airbyte SAP (RFC)
35SAP Business OneService Layer RESTJournalEntries (JDT1)BudgetScenarios (Service Layer)Airbyte HTTP
36ERPNextFrappe REST APIGL Entry doctypeBudget doctype (Frappe API)Airbyte ERPNext or direct Frappe API

Architecture

Raw ERP Data (Airbyte / direct API)

Per-ERP Adapters (models/staging/<erp>/)

Canonical Staging (models/staging/canonical/) ← UNION ALL from adapters

Bronze → Silver → Gold (unchanged, ERP-agnostic)

D365 Budget Write-Back

On budget approval in Frappe, push the approved budget to D365 F&O via OData POST to BudgetRegisterEntries.

Source of Truth Decision:

ConcernSource of TruthRationale
Budget planning & scenariosClickHouse (via Frappe)Multi-layer budgets (base/challenge/management/board), spreading profiles, scenario modeling — none of this exists in D365
Actuals / GLD365 (synced to CH via Airbyte)ERP owns transactional data
Budget vs Actuals reportingClickHouse (has both)Single query engine for all analytics
Budget control in ERPD365 (receives approved budget)D365 uses BudgetRegisterEntries for PO/expense validation

ClickHouse is the authoritative store for budget. D365 is a downstream sync target — a one-way push so D365's native budget control features have the numbers.

Round-trip prevention: Do NOT Airbyte-sync BudgetRegisterEntries back from D365 into epm_raw. If syncing is required for audit, tag EPM-originated entries (e.g. BudgetModelId = 'EPM') so dbt can filter them out.

Implementation:

  • Frappe hook on Budget Input workflow transition to "Approved" → triggers async write-back
  • D365 OData POST: map flat budget rows to BudgetRegisterEntries header + line format
  • Dimension mapping: entity, account, cost center, dept → D365 LedgerDimensionValuesJson
  • Error handling: D365 validation failures (closed posting period, invalid account) → log to Budget Input doctype
  • Idempotency: tag entries with EPM budget ID to allow re-push without duplicates
  • Config: D365 connection settings in Frappe (Azure AD tenant, client ID, resource URL) — reuse Airbyte credentials pattern

Scale Architecture

For deployments with 50–500 legal entities across multiple ERPs:

  • Partitioned bronze tablesbronze_general_journal_account_entries partitioned by toYear(accounting_date), budget by toYYYYMM(transaction_date), FX by toYear(valid_from)
  • Parallel dbt builds — per-ERP adapter builds can run concurrently (adapter pattern supports this)
  • Incremental extraction — Airbyte CDC for high-volume ERPs (SAP, D365)
  • ClickHouse cluster — sharded by entity_id for horizontal scale
  • Monitoring — per-connector health dashboard in Frappe

Phase 4: Security & Entra ID SSO (~2 days)

PRD: Security & Microsoft Entra ID SSO

4.1 Entra ID Integration (1 day)

  • Register Konsol in Microsoft Entra ID (OAuth2 / OpenID Connect)
  • Map Entra ID groups to Frappe roles (Reader, Planner, Controller, Admin)
  • Test SSO login flow

4.2 Reverse Proxy & TLS (0.5 days)

  • Caddy in docker-compose: auto-cert TLS, CORS for Excel Online
  • Rate limiting: 100 req/min per user

4.3 ClickHouse Network Isolation (0.5 days)

  • ClickHouse on Docker internal network only (no host port bindings in production)
  • Verify: no ClickHouse ports reachable from public internet

Phase 5: Excel Online Add-in (~3 days) DONE

Task pane add-in built and deployed. Source: excel-addin/, served from Frappe public/excel-addin/.

  • Office.js Task Pane app (manifest.xml, taskpane.html/js/css, icons)
  • Frappe session-based authentication (login/logout via cookie)
  • Pipeline orchestration: trigger Extract + dbt Build, poll status (5s interval)
  • Status display: Queued/Extracting/Transforming/Success/Failed badges
  • Deployed to Frappe static assets, sideloadable via manifest.xml
  • Documentation: README + user guide + architecture diagram

Not included (by design — VBA handles data):

  • No custom functions (=EPM() stays in VBA for desktop, Office.js for pipeline control)
  • No MSAL/OAuth (uses Frappe session cookies instead)

Phase 6: Analytical Gaps (~2 weeks)

6.1 Cash Flow Statement (2–3 days)

PRD: Cash Flow Statement (Indirect Method)

  • gold_cash_flow_indirect.sql — derive from balance sheet delta method
  • Categories: Operating, Investing, Financing
  • Account mapping seed: cash_flow_categories.csv
  • Consolidated cash flow (after FX translation)
  • Tests: operating + investing + financing = net change in cash

6.2 Multi-GAAP / Dual Reporting (1 week)

PRD: Multi-GAAP / Dual Reporting

  • reporting_standard dimension (LOCAL_GAAP, IFRS)
  • Separate adjustment rules per standard
  • Gold models produce one output per standard
  • Tests: each standard balances independently

6.3 Rolling Forecasts (2–3 days)

PRD: Rolling Forecasts

  • 12-month forward window, shifts monthly
  • Actual for closed periods + forecast for open periods
  • Scenario type rolling

6.4 Budget Cell Locking (1–2 days)

PRD: Budget Cell Locking (Concurrency Control)

  • Optimistic locking: check modified timestamp on budget_cell_save() — reject if stale
  • Conflict response with latest value so Excel can prompt user
  • Optional pessimistic locking: Budget Lock doctype with auto-expiry (5 min)
  • VBA retry logic on conflict (refresh cell, re-prompt)

6.5 Multi-Step Budget Approval Chain (0.5 day)

PRD: Multi-Step Budget Approval Chain

  • Extend budget_input_workflow.json: Draft → Submitted → Dept Manager Approved → Controller Approved → CFO Approved
  • Each transition gated by a separate Frappe role
  • Use Frappe docstatus = 1 (Submit) on final approval to permanently lock document
  • Email notifications on workflow state changes (Frappe Notification doctype)

6.6 Consolidation Enhancements (1–2 weeks)

PRD: Consolidation Enhancements

  • Historical (temporal) rate for equity line items — IAS 21 equity translation at acquisition-date rates
  • Remeasurement vs translation distinction (separate functional currency handling)
  • Goodwill CTA — CTA on goodwill arising from acquisition accounting
  • Recycling CTA to P&L on disposal of a foreign operation
  • NCI in business combinations — goodwill allocation to NCI (full vs partial goodwill methods)
  • Changes in ownership without loss of control — equity transactions between parent and NCI

6.7 Allocation Enhancements (3–5 days)

PRD: Allocation Enhancements (Circular & Reciprocal)

  • Circular (iterative) allocations — convergence-based solving for reciprocal cost pools
  • Reciprocal allocation method — simultaneous equations approach (alternative to iteration)

6.8 Planning Enhancements (1 week)

PRD: Planning Enhancements (Driver-Based & Recurring)

  • Driver-based planning — revenue × price × volume decomposition
  • Phasing templates at account-group level (apply seasonal patterns by account type)
  • Recurring journal templates — auto-generate topside journals on schedule
  • Topside journal approval workflow (separate from budget approval)

6.9 Reporting Enhancements (3–5 days)

PRD: Reporting Enhancements (Waterfall, Trend, Commentary)

  • Waterfall / bridge analysis — price, volume, mix decomposition of variances
  • Trend analysis — period-over-period and rolling averages
  • Commentary / annotation on variances — attach narrative to variance cells

6.10 Close Assertion Suite — Reconciliation Gate (3–5 days)

PRD: Close Assertion Suite — Reconciliation Gate

Every close runs against an automated assertion suite. Green means the numbers reconcile; red tells you exactly which row broke, and why — before anyone signs off.

  • Surface the 60+ existing dbt assert_* tests (BS balances, CTA, IC elimination, equity method, allocations, hierarchy ties) as a named, per-close assertion suite, run on a Pipeline Build Request via dbt build / dbt test --store-failures
  • Close Assertion Run doctype — one row per assertion with pass/fail (green/red), category, and a link to its failing rows
  • Capture the failing rows + reason from dbt --store-failures (the offending entity/account/period rows — not just "a test failed")
  • Close sign-off gate — block close approval (ties into the budget/consolidation approval chain, §6.5) until the suite is green, with an explicit, audited override
  • Dashboard — green/red board per close period; drill a red assertion into its failing rows

Builds on what already exists: the tests/**/assert_*.sql suite, gold_ic_reconciliation, and the Pipeline Build Request governed-build path. Net-new work is capturing/parsing dbt test results into the app and the sign-off gate UI.


Phase 7: Production Hardening (~3 days)

PRD: Production Hardening

  • ClickHouse backup automation (scheduled snapshots to Azure Blob / S3)
  • Monitoring: ClickHouse query latency + Frappe response times (Prometheus + Grafana)
  • Alerting: email/Slack on pipeline failure or dbt test failure
  • Load testing: simulate 50 concurrent Excel users
  • Runbook: monthly close process
  • Disaster recovery procedure

Effort Summary

PhaseEffortDependencies
Phase 1: One-click deploy~3 daysNone
Phase 2: Dynamic schema (dimensions, measures, facts)5 days ~1 day remaining (Dimension/Measure auto-DDL, Budget Input form)None
Phase 3: Multi-ERP (4 connectors remaining + scale)8 weeks ~5 weeks remainingPhase 2 (dimension abstraction)
Phase 4: Security & SSO~2 daysPhase 1
Phase 5: Excel Online Add-in3 days Done
Phase 6: Analytical gaps, consolidation/allocation/planning/reporting enhancements~6 weeksPhase 2 (dimensions)
Phase 7: Production hardening~3 daysPhase 1
Total~7 weeks

Phases 1 and 2 can run in parallel. Phase 3 depends on Phase 2 (schema abstraction). Phases 4–7 can overlap.